Source
Department for Transport — Local road maintenance ratings 2025 to 2026
Hertfordshire County Council spends roughly three times its DfT capital allocation and earns a GREEN scorecard for spend. Yet the overall rating is AMBER — because RED-condition B roads more than doubled in a single year, 18% of unclassified roads needed maintenance at the last published survey despite a £29m improvement programme, and pothole repairs are up 49% in five years.
Six years of survey data from Hertfordshire's own transparency report — A roads holding steady, B roads falling off a cliff
Credit where due: main roads are machine-surveyed every year and have held steady. But A roads are only one-seventh of the network.
| Year | Red | Amber | Green |
|---|---|---|---|
| 2019/20 | 3.5% | 22.3% | 74.2% |
| 2020/21 | 6.3% | 27.7% | 66.2% |
| 2021/22 | 2.8% | 19.6% | 77.7% |
| 2022/23 | 3.0% | 21.0% | 76.0% |
| 2023/24 | 3.2% | 22.4% | 74.4% |
| 2024/25 | 7.0% | 31.0% | 62.0% |
In a single year, RED-condition B roads jumped from 3.2% to 7.0% — the worst figure in six years of published data — and good-condition B roads collapsed from 74.4% to 62.0%. These are machine-survey figures, not estimates. Over a third of the B road network now needs, or will soon need, maintenance.
C roads improved to 4.5% RED in 2021/22, then gave the gains back: by 2024/25 they were at 6.0% RED — level with 2019/20 — and 35% of the C network was RED or amber combined.
Hertfordshire spent over three times its DfT allocation in 2024/25, and projects £90.9m of capital spend for 2025/26 — yet B and C roads are still declining and pothole repairs keep rising. The problem isn't the chequebook. The network is deteriorating faster than even a GREEN-rated spend programme can hold back.
64% of the network is unclassified roads — and they're now in worse shape than before the council's five-year improvement programme began
| Year | U roads in the RED category |
|---|---|
| 2016/17 (£29m programme start point) | 16% |
| 2017/18 | 10% |
| 2018/19 | 9% |
| 2019/20 | 7% |
| 2020/21 | 12% |
| 2021/22 | 7% |
| 2022/23 (target was 8%) | 10% |
| 2023/24 (latest published) | 18% |
Hertfordshire committed "an additional £29m over five years to improve the unclassified network" with "the ambition to halve the percentage of roads that should be considered for maintenance" — from 16% in 2016/17 to a target of 8% by 2022/23.
The actual 2022/23 figure was 10% — target missed. A year later it hit 18% — higher than the figure the £29m programme set out to halve. On a 3,244km unclassified network, that is roughly 580km of residential streets, estate roads and rural lanes in the "maintenance should be considered" category.
Unlike A, B and C roads, which get machine surveys, the council's own report says U-road figures "are usually based on a more subjective visual inspection by accredited inspectors" and "show greater change from year to year".
To its credit, Hertfordshire surveys all unclassified roads every year — many councils don't. But the council itself flags that the method is subjective, and it plans to phase out visual inspections for automated technology under new DfT guidance. The condition record for two-thirds of the network rests on the weakest survey method available.
To rely on the Section 58 defence, a council must show it had a reasonable system for knowing the condition of its roads and acting on it. For Hertfordshire's unclassified network, ask:
A council that watched its unclassified network deteriorate past its own programme's start point cannot easily argue the deterioration took it by surprise.
The scale of reactive repair tells you how many potholes this network produces — and the trend is sharply upwards
| Year | Estimated pothole repairs | Per day |
|---|---|---|
| 2020/21 | 26,037 | ~71 |
| 2021/22 | 26,560 | ~73 |
| 2022/23 | 26,195 | ~72 |
| 2023/24 | 37,854 | ~104 |
| 2024/25 | 38,806 | ~106 |
| Five-year total | 155,452 | ~85 |
Repairs ran at a steady ~26,000 a year for three years, then jumped 46% in 2023/24 and stayed there. A network producing well over a hundred pothole repairs a day is, by definition, a network where defects routinely form between inspections — exactly the scenario where prior reports and photographic evidence decide claims.
The council's own explanation for the jump: "In 2023/24 we allocated additional funding to address more carriageway defects. It was directed towards lower priority defects that did not meet assessment criteria for an urgent Cat1 pothole repair." In plain terms: there was a known backlog of sub-urgent defects sitting on the network — large enough to need its own funding line.
The council's own explanation for the U-road collapse — in its own words
"The increase in the score for the number of unclassified roads requiring treatment in 2023/24 was due to the weather which has significant impacts on the road network. Extreme heat, cold, precipitation has significantly damaged the unclassified road network."
— Hertfordshire County Council Local Highways Maintenance Transparency Report, June 2025
"Much of the unclassified road network is referred to as 'evolved' where it could have been a historic track that has been made up over a number of years, rather than being a 'designed' road. The foundations of undesigned roads are much more susceptible to damage if moisture is allowed to penetrate through the surface."
— Hertfordshire County Council Local Highways Maintenance Transparency Report, June 2025
"Changes in our weather patterns are producing more extreme peaks and prolonged periods of high temperature, wet weather and other factors that can contribute to and accelerate carriageway deterioration. The composition of many of our carriageways was not designed to cope with these conditions."
— Hertfordshire County Council Local Highways Maintenance Transparency Report, June 2025
Hertfordshire formally acknowledges that a large part of its unclassified network sits on undesigned foundations that fail faster when water gets in, and that today's weather is accelerating deterioration across the carriageway stock generally.
Knowledge of accelerated, weather-driven deterioration on a known-vulnerable road class raises the standard for what a "reasonable" inspection and repair regime looks like on those roads under Section 58 — particularly after wet or freezing spells, when potholes form fastest.
Hertfordshire's repair commitments are genuinely better than many councils' — but read the small print
"In Hertfordshire we aim to carry out a permanent repair to urgent potholes, cutting out the defective material and replacing with new within 1 to 4 weeks of the defect being identified, rather than carrying out a temporary fix that may need repeating. Over 90% of our urgent potholes are fixed with a first-time repair using hot material."
— Hertfordshire County Council Local Highways Maintenance Transparency Report, June 2025
First-time permanent repairs with hot material are best practice — temporary cold-fill patches that crumble within months are a common failure mode elsewhere. If Hertfordshire genuinely fixes 90% of urgent potholes permanently first time, that's a real strength, and you should expect the council to document it in any Section 58 defence.
Everything in that commitment hinges on the words "urgent" and "identified". The report says repairs are prioritised by risk assessment, and that "a shallow pothole on low use rural road will not be such a high priority as a deeper pothole on a main A road."
A defect that hasn't been identified gets no clock at all. A defect assessed below the urgent Cat1 threshold joins the lower-priority queue — the same queue that built up a backlog big enough to need additional funding in 2023/24. And even an identified urgent pothole can lawfully sit in the carriageway for up to four weeks. If your incident falls in any of those gaps, the repair policy doesn't defeat your claim — it frames it.
Honest assessment: Hertfordshire runs a serious asset-management operation — here's how that changes your approach
Expect a well-documented Section 58 defence with inspection records and risk assessments. Generic claims will struggle here.
Against a council with a GREEN spend record and a professional asset-management operation, your claim lives or dies on the specific defect:
Mac builds exactly this case: he searches for prior reports, assesses your photo evidence, and cites Hertfordshire's own transparency data where it helps you.
A well-run council demands a well-built claim. £35 for a professional claim pack.
No percentage fees. You keep 100% of any compensation.
Yes. The DfT Spend scorecard is GREEN — Hertfordshire spent £85.2m of capital in 2024/25 against a £25.7m DfT allocation. But the overall rating is AMBER because of road condition: RED-condition B roads more than doubled in a year and 18% of unclassified roads needed maintenance at the last published survey. Section 58 turns on whether the specific defect that damaged your vehicle was reasonably inspected and repaired, not on aggregate spending.
Unclassified roads make up 3,244km — nearly two-thirds of the Hertfordshire network. At the last published survey (2023/24), 18% were in the RED category, the worst figure since 2016/17 and worse than the 16% start point of the council's own £29m five-year improvement programme. The council also notes U-road figures come from "a more subjective visual inspection" rather than machine surveys.
In 2024/25, B roads in the RED category jumped from 3.2% to 7.0% — the worst figure in the six years of published data — while B roads in good condition fell from 74.4% to 62.0%. If your pothole was on a B road, the council's own machine-survey data documents rapid, recent deterioration across that road class, which is directly relevant to whether its maintenance response was reasonable.
No. That commitment applies only to defects already identified and risk-assessed as urgent Category 1 potholes. The real questions are whether your pothole was identified at all before your incident, whether it was risk-assessed correctly, and how long it sat below the "urgent" threshold. The council's own report says a shallow pothole on a low-use rural road "will not be such a high priority" — and lower-priority defects built up such a backlog that extra funding was allocated in 2023/24 to deal with them.
Yes. Hertfordshire's transparency report states that much of its unclassified network is "evolved" — historic tracks made up over the years rather than designed roads — and that "the foundations of undesigned roads are much more susceptible to damage if moisture is allowed to penetrate through the surface." That is documented knowledge that a known class of roads deteriorates faster, which raises the bar for what a reasonable inspection and repair regime looks like on those roads under Section 58.
Hertfordshire filled 26,037 potholes in 2020/21 and 38,806 in 2024/25 — a 49% increase, averaging 106 repairs every day in the latest year. The council explains part of the jump itself: in 2023/24 it "allocated additional funding to address more carriageway defects... directed towards lower priority defects that did not meet assessment criteria for an urgent Cat1 pothole repair". In plain terms: there was a known backlog of sub-urgent defects on the network large enough to need its own funding line.
Data sources: Department for Transport — Local Road Maintenance Ratings 2025 to 2026 | Hertfordshire County Council Local Highways Maintenance Transparency Report (June 2025). Contains public sector information licensed under the Open Government Licence v3.0.
Reusable evidence record
Rating period: 2025-2026 · Reviewed 19 July 2026
Department for Transport — Local road maintenance ratings 2025 to 2026
Overall AMBER; condition AMBER; spend GREEN; best practice AMBER.
This is network-level context. The rating does not determine liability for a particular incident or establish what was known about a specific defect.
Correction status: No correction recorded.